Monday, 30 March 2015

A list of suppliers and trades that contributed towards our Selfbuild

A little after it was intended, but here is a list of the suppliers and trades we used during our self-build. Some of these supply nationwide, but lots are based locally in our beautiful county of Herefordshire.

The list in no particular order (hopefully including everyone who contributed towards our self-build), with an outline description of what they did/had input towards towards are:

Mark Littleworth of MGL Building, Leominster (Base, General Building, Brick/Block Work) 07971850680

Neil Smillie, Bromyard (General Carpentry, 1st & 2nd Fix) 07977093162

Border Oak, Kingsland (Oak frame, timber framed shell, roof, doors & windows) 01568708733

Neil Littleworth, Plumbing & Heating (Plumbing & underfloor heating) 07889093188

Sid Littleworth @ Courtyard Designs, Risbury (Oak Stairs, Oak Window Boards) 07710156095

Stuart Carter Furniture, Tenbury (Custom made wardrobe, softwood cupboard doors, ledge and brace doors) 07971325921

Gareth @ GRM Electrical, Tenbury (1st & 2nd Fix electrics) 0751763961

Travis Perkins Leominster (General Materials & Tools throughout the build) 01568612531

Eclisse (Pocket Door) 01476565497

Powell & Co Timber Merchants, Kingsland (Timber cladding & general timber for internal stud walling etc) 01568708819

Goode Brothers Timber Merchants, Mortimers Cross (Oak Doors, Oak Door Linings, Oak Skirting Boards, Oak Architrave) 01568708382

Dave Goodfield Decorating & Plumbing, Leominster (Tiling / Decorating) 07974284041

Stan Stones, Hereford (Stone floor tiling, wall tiling)  07912938850

Balustrade UK, Dudley (Glass Balustrade for stairs/landing) 01384252342

Aella @ Boyd Scaffolding, Craven Arms 07525772696

Devant Designs, Hereford (Floor & Wall Tiles) 01432355377

Discovery Tool Hire, Leominster 01568613188

Ian Godding @ Hitrees Building & Landscaping, Bicton 07885839348

Owen Hicks Architects, Hereford (Building Regs Drawings & Architects Certificate) 01432261152

Tony Jarman, Leominster (General building) 07802422571

Garry @ Herefordshire Drylining (Plaster boarding, tape and jointing) 07831121459

Kingspan Insulation, Pembridge 01544388601

Fontura Worktops, Leominster (Kitchen Worktops) 07738934354

Crown Decorating Centre, Hereford (Paints internal / external) 01432276254

Leominster Pest Control 01568615249

Shaun @ Acorn Construction (Flowing floor screed) 07971116817

Stuart Rye, Ironbridge (Building air test) 07976372271

B & Q Hereford, Kitchen & Bathroom 01432277630

Bill Sommers Mortgages, Leominster 01568614477

Rowlands Roofing, Hereford 01981251590

Kai Stevens (Stone scalpings, aggregates etc) 07966083181

Bromfields Sand & Gravel 01584856258

Wills Engineering, Leominster (steel for our table) 01568616303

Hyde Brothers, Wooferton (Plumbing Supplies, Septic Tank) 01584711713

Howdens Leominster 01568614904

Beryl Beaumont (Curtains & roman blinds) 07870329469

Apologies if I have forgotten anyone, if you want to be added to this list please contact me.

Best regards, Tim

Tuesday, 21 October 2014

Finally we're ont'elly... how did that happen?

11 months from when we first put a hole in the ground to start the foundations, we managed to move in and along the way build our dream home with the help and skills of some fantastic, friends, family and trades. We managed to do quite a bit of the work ourselves, found skills we didn't know we had, build it on budget (which was good, because we didn't have an extra few million to cover an over spend) and on time - not bad for someone who fixes cars!

Over the last few weeks I have contemplated what we have achieved (with the help of a quite few others) and it feels amazing to finally be living in our house. We poured our hearts and souls into the build and with the exception of the garden there isn't that much left to sort out. On the whole, I think we managed to stay pretty positive throughout the build with the relatively small issues experienced paling into insignificance when we look at what we've managed to do. Managing the build alongside working has been very challenging, emotional, sometimes frustrating, really exciting, great fun and at times very tiring, but extremely rewarding. Every success and imperfection we've had a significant part in. Not many people are lucky enough to build their own house and we feel very privileged to have done so. If anyone gets the chance, is prepared to make sacrifices and put in some hard work they should jump at the opportunity!

We were lucky enough to have our build recorded by the talented (not just with the camera) and generally nice fellow Lee Chapman. Thanks to Lee's filming along with the input from the rest of the True North Production team our house build will be visually documented forever. Lee who was on site with us regularly throughout -  helped us to adapt to being filmed with a massive lense in our little faces, keeping it relaxed and interesting and without impacting on progress. It is nice to think we have made a friend through one of the most significant 12 months of our lives and I am sure we will keep in contact in the future. Charlie, Christian, Stokey, Sally, Hayley among others at True North made our self-build journey fun, kept us (and some of the trades) on focus and on time along with providing us with some fantastic improvements to our home, which we wouldn't have thought possible and/or affordable - thanks for that Charlie, we didn't see it initially but in most cases you (and Fliss) were right.

While building, Fliss also managed to plan our wedding and while I moaned and groaned about help with the house on times, she managed to pull off a perfect day and the start of the next (hopefully slightly more relaxed) chapter of our lives together.

A massive thank you to everyone at True North and the friends, family, work colleagues, companies and trades who made it all possible. Here are some sneaky pics of our house which will be on later today, Tuesday 21st October 2014 - 9pm on More4 "Building the Dream."

 House designed, frame and shell erected by Border Oak with design drawings tweaks by Owen Hicks Architecture 
Open plan living space
Oak stairs made by Courtyard Designs, brushed Nickel handrail from Ironmongery direct and glass  from Balustrade UK

Liv's wardrobe handmade by Stuart Carter Furniture and painted by us
 Josh's bedroom not too messy yet
Bathroom tiles from Devant Designs, Hereford, Bathroom suit etc mixed and matched from various suppliers including reclaimed.

We love our new home. I hope you enjoy the programme as much as we enjoyed being part of it...

I will compile a list in a future blog with links where possible of the trades, companies and suppliers who we used along the way. Bye for now...

Thursday, 16 October 2014

Filling in the blanks... part due

July 2014, we were now frantically getting ready to move in. All the major works on the house were completed but it is amazing how much time the finishing (and preparing to finish) takes. July seemed to be a really good month for progress, with very visible things happening. 

Starting with the upstairs bathroom. After watching the dry lining being done I decided that I would have a go myself in the upstairs bathroom and made the frame, fixed the plasterboard and tape and jointed. At best it would look alright and at worst it was in the back of the bathroom so wouldn't matter anyway! I don't think it ended up too bad and we have another useful little storage box. 

A bit messy but looks OK, pipe work boxed in
Bathroom floor down ready for painting and tiling
Oak shelf, cut, fitted, oiled and ready for the bathroom suite and radiator 
Tiling taking shape
Reclaimed toiled and sink plumbed in and fitted. Radiator sat on the oak shelf.
Bathroom feature wall
Josh's room all cleaned up and ready for underlay and floorboards to go down.


Nearly there, last couple of boards and Josh room floor will be done
Engineered oak flooring in Olivias room , starting to look like a home upstairs
We've put the same engineered flooring through the upstairs rooms 

While the upstairs progressed, downstairs the Oak architrave and skirting boards also were being fitted. The oak was sourced from a local timber yard just down the road in Mortimers Cross (Good Brothers). We used them for quite a bit of the internal oak finishes as I found them very helpful and the timescales they were able to turn around orders also suited our build. I also hadn't forgotten how they managed to turn around the door linings within a couple of days earlier in the build, which meant the plaster boarding wasn't delayed. 

Oak architrave and skirting boards downstairs
Mitred joints and screw and plug fixing
Caps ready to fill the holes in the oak
Oak ledge doors hung
The quartze worktop supplied and installed by Fontoura in Leominster. Just 7 days from the templating the worktop was installed and the kitchen started to feel like a useable space. 

While the inside progressed a lot was happening on the outside as well.

The sceptic tank - we now have somewhere for the waste to go, which is the last thing that would enable us to move in. 
 Lighting up the oak and sitting area outside the french doors. When we have time for BBQs!
Outside lights by the front and rear doors. A bargain of the interweb. 
Really happy with the Lindab galvanised steel guttering, especially against the roof tiles and grey timber cladding. 

Thats it for now, thanks for looking! Tim 

Thursday, 9 October 2014

Filling in the blanks... part uno

I am going to use the next couple of blogs to fill in some of the blanks I missed to write about when we were in the throws of the finishing the house off. We simply didn't have enough time to write properly, but I made some notes and took some photos along the way so I could come back to it later (well now really).

The first of the missing blogs is June 2014. We started to make some progress downstairs that made it feel more like a house than a shell. With the electrics and plumbing first fix sorted, the tiles on the floor we were able to fit the kitchen and the delay in the floor tiles meant that we were able to use the time for Stan Stones to tile the shower room. I fitted most of the kitchen myself, very therapeutic when it goes to plan...

The kitchen has finally been moved into the right part of the house, while we start to assemble units before moving them out of the way to start fitting the units.
 The first and most difficult unit on the who kitchen is put into position and fixed
 Washing machine & dishwasher spaced as the other units go in
We have the bare bones of a kitchen
 The shower room tiling is well under way, with the glass tiles forming the back wall of the shower
Holes in the wall, sealed and tiled
Tiles grouted and ready for the shower, screen, toilet and sink
While the downstairs moves on, Fliss and Mum wallpapered Josh' bedroom

Thanks, for reading the next blog will be soon!

Monday, 1 September 2014

We're in, filmed and the caravan is away...

As I write this post we are now officially in our new home. The Caravan has been re-homed approx 9 miles away (for another home renovation/building project), we've done the last batch of filming for our "Building the Dream" reveal and we have confirmed dates we'll be ont' telly (14th October at 9pm on More 4).

I've made some notes of bits I've missed to blog about, but will definitely come back to those at a later date - for those that are interested and also for our own records in time to come.

I can't tell you how amazing it feels to be finally living in our house, with luxuries like hot water (without the risk of gas running out), heating, a kitchen and dining table big enough to actually use and a bath... Fliss and I are delighted with how it has all come together (just in the nick of time) and it's a good job too because in less than 2 weeks we get married. We've managed to build and be in within 12 months of starting the foundations and to keep to our budget without compromising too much on the finish on the house. The caravan going has really opened up the plot and given us our views back.

It has been absolutely manic trying to get everything finished - firstly so the caravan could move on, secondly so we could actually move in and have bedrooms fully functioning so the kids can sleep in them and thirdly so we were ready for the big reveal filming session. I can't thank my Mum and Dad and also a few of the trades who worked tirelessly to help ensure we were ready for filming.

I also wanted to give a special mention to Stuart Carter of www.stuartcarterfurniture.com who selflessly turned up the day before filming to finish off a couple of jobs for me (with some oak architrave and an oak moulding for the stairs that he rushed through his workshop in the morning for me) and ended up being here nearly all day doing a "few little jobs more". You can tel Stu loves what he does, because not only are the wardrobes and doors he made for us really lovely - he also told me he'd "had fun today." Not sure everyone would have thought the same when they went above and beyond the call of duty.

I am going to try and give some pictures, without giving away too much for the reveal. 

Friday, 18 July 2014

Quick progress update and the money tree

When I started to write this blog on the 10th of June, I got halfway through it and parked it to one side. We had seen slower progress on site, we were waiting for the remainder of the floor tiles to arrive, the remainder of the glass tiles for the shower room (we had 4 tiles that weren't square on the corners and www.stanstones.co.uk sent them back) and the kitchen water and gas carcassing to be carried out.

We took the opportunity to do some more painting (including a re-paint with slight colour change on the triangular areas over the beams) and organise the upstairs bathroom tiling. I've also had a chat with http://www.stuartcarterfurniture.com about the storage problem we have upstairs and so we could see what is affordable (triangular roof shapes, don't make wardrobes too easy). We discussed what we could do and what we were looking for and pricing and we commissioned him to build our upstairs wardrobe along with custom made doors for the storage under the eaves and for the upstairs bedrooms.

That leads on to the budget. I've also been looking at our numbers and whilst I am quietly confident we will still come in on budget, we are however starting to feel the squeeze and decisions will need to be made about what we can afford - at the most difficult time to keep a check on it. We are really happy with the decisions we have made throughout the build, but the money tree isn't fruiting and short of winning the lottery we need to keep the budget in mind. When/if we do manage to come in on budget, I'll be pretty pleased considering this is the first time we have built.

Since starting this blog everything has been moving along at 100 miles per hour, we've now got a fitted kitchen, shower and bathrooms, flooring downstairs, flooring upstairs, skirting boards and door architrave downstairs (and some upstairs), our LPG gas bottle is installed underground, we have a septic tank that is plumbed in and storm drains are pretty much sorted.

We really are just weeks away from being able to move in, but we are still hanging on to complete as much as possible without being tempted to move in before we are finished inside... whats a few more weeks after nearly 4 years in a caravan on site?

Monday, 2 June 2014

Colouring the walls and tiling the floor... we've finally completely agreed on something!

We've had quite a bit of activity on site in the last couple of weeks- at one point we had tilers, electricians, a plumber and us working (note to self whilst it sounds a good idea, with a house our size we were nearly tripping over each other). We've painted all of the house with a least a coat of watered down paint for the plasterboard, with most of it having a least 2 coats already. The main living space walls and ceilings fully painted, the bathroom and shower room also fully painted - just touching up to do one most of the works has been finished. We have also oxalic acid cleaned the internal oak beams and given them a coat of wax oil.

Oak beams cleaned and wax oiled

We've dug the water main into the house and the electrics to the boundary and laid a pipe to pull the BT cable through once we are out of the Caravan.


Whilst we've been doing all of that, the main living space has been tiled with our 600x600 limestone tiles they have been laid, sealed, grouted, cleaned and as I'm typing this the final coat sealer is drying - we've had a slight problem with the half of the tiles still not arrived (luckily enough have arrived for most of the living space to be done, which means we will able to make a start on moving the kitchen back into the house later in the week, we're still waiting for the remaining shipment to arrive in the UK from Germany).

STOP PRESS: It's now I need to drop the bombshell that the floor tiles was the first thing we jointly chose and completely agreed on throughout pretty much the whole build! Even better is that now they are down, we are still delighted with our choice - both of us! Obviously as things have progressed we haven't disagreed on everything, but in terms of picking a finishing product we both loved them almost as soon as we saw them. We chose Jura Grey Limestone 15mm Floor tiles and did quite a bit of hunting around to get them.

We ordered them from a local supplier to find out that they weren't available quick enough so I reverted to trawling the net and found enough to get us to the point that we could start on the kitchen. We've also been very pleased with the tiling and have been lucky to find a tiler http://stanstones.co.uk/ who comes highly recommended locally - and so far, so good!

Cut around the naughty step
1st coat of sealer ready for grouting
The kitchen area is tiled

The pipework on the shower has been carcassed prior to the tiling. The shower room has been partially tiled and should be finished tomorrow.

We've been trying to organise a supplier for the glass balustrade on the landing, but this is proving more expensive than anticipated. We really hope we can afford to do it, but we still need to do some work on this.

It really does feel like we are on the home straight now, still plenty to do but getting closer every day.

TTFN, Tim