Wednesday 15 January 2014

First delays... a new experience for our build

The build has been moving along so well, in terms of timing and things being done as expected, but this week we have seen our first real setback.

We were due to have our windows and doors fitted next week, but due to flooding in the factory there has been a delay that is likely to mean we will fall several weeks behind where we thought we would be on the external side of the build. I realise it isn't anyones fault, but that doesn't mask the disappointment Fliss and I felt on Monday when we found out. We'd been really looking forwards to getting the windows fitted! It's the first date on the build that hasn't been met, which is a new experience for us.

The consequence of the delay will impact on other work, we had scheduled the remaining brick work to be completed this week (which is still on track), following on with windows and doors next week and then first week in February the external weather boarding to be done - which would have meant by mid February the house would be completely water tight... hopefully the delay won't push us too far back into worse weather.

The scaffolding is now completely down internally and externally, which revealed the house more fully on the outside and gave a sense of the space inside. We are both delighted with how it is taking shape and pleased with the colour we've been painting on the exposed softwood timbers. As well as Fliss and I painting weather board (52 down, just another 32 to go), I've been quietly carrying on with the insulation in the roof over the last week or so. It's coming along but is a slow process when your are doing it around a normal working day. I had Dad helping again last Saturday, which has made a big difference.

I've got a day off on Friday to help start to do the downstairs stud walling and a bit more on Saturday so we are ready for first fix plumbing  last week in January and then moving on to electrics.

So, by the end of this month we should have all the house external brick work completed, all the internal stud walling in place and the first fix plumbing done. We will also have done a bit more filming for our mentor visit to another house!

Finally I just wanted to thank you for reading, since the blog started we've now had over 4000 views!